100 MW BESS operating in Brazoria, TX
100 MW
Nameplate Capacity
1
Generators
unit
Batteries
Technology
2021
Operating Since
Coordinates
29.1682, -95.4458
County
Brazoria, TX
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Gambit Energy Storage LLC | — | — |
| Owner(s) | Gambit Energy Storage LLC | — | — |
| Status | Operating | — | — |
Gambit Energy Storage - Angleton Storage is a 100 MW battery energy storage system (BESS) located in Brazoria County, Texas. The plant began operating in 2021 and is owned and operated by Gambit Energy Storage LLC. It is interconnected to the Electric Reliability Council of Texas (ERCOT) grid, within the Texas Reliability Entity (TRE) NERC region. The facility utilizes lithium-ion batteries (LIB) and has a total storage capacity of 200 MWh, providing a duration of 2 hours at full output.
The Angleton Storage facility is ranked as the 211th largest power plant in Texas out of 224, and 494th nationally out of 514. The plant consists of a single generator and uses "MWH" as its primary fuel, indicating that it draws power from the grid to charge its batteries.
Generated from EIA, GEM, and public data sources
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
Electric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
138.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
−719 MWh
Net Charging
-14.5K MWh
Annual Net Energy
-1.7%
Capacity Factor
Positive values indicate net discharge (generation exceeds station load). Negative values indicate net charging. Pure battery storage plants are typically net negative due to round-trip efficiency losses.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2021
$1,796/kW
Est. Construction Cost
Total estimated cost: $179.6M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
ERCOT
LMP Node
GAMBIT_RN
Pricing Hub
HB_HOUSTON
Alt. Hub / Zone
LZ_HOUSTON
Location Type
Resource Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-03-26
View all 7 articlesNo Ask reports yet for this entity.
Ask about Gambit Energy Storage - Angleton StorageForward forecasts, scenario decomposition, and risk-decision tooling for this asset.