3.2 MW Natural Gas operating in Somerset, NJ
3.2 MW
Nameplate Capacity
1
Generators
unit
Natural Gas Internal Combustion Engine
Technology
2019
Operating Since
Coordinates
40.5704, -74.6395
County
Somerset, NJ
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Onsite Partners, LLC | — | — |
| Owner(s) | AEP Onsite Partners, LLC | — | — |
| Status | Operating | — | — |
The LabCorp Engine is a natural gas-fired power plant located in Somerset County, New Jersey. The plant has a total capacity of 3.2 MW and began operating in 2019. It consists of a single natural gas internal combustion engine generator. AEP Onsite Partners, LLC is the plant's operator.
The LabCorp Engine operates within the PJM Interconnection, LLC balancing authority and the RFC NERC region. In terms of size, it ranks 40th out of 46 power plants in New Jersey, and 1675th out of 1963 plants nationally. The plant's latest annual generation was 235 MWh, resulting in a capacity factor of 0.8%.
Generated from EIA, GEM, and public data sources
ISO/RTO
PJM
Market
ISO/RTO Member
NERC Region
RFC
Balancing Authority
PJM Interconnection, LLC (PJM)
Grid Voltage
13.2 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
16 MWh
Latest Month
235 MWh
Annual Generation
0.8%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
CO₂ Intensity
1451 lb/MWh
Low-utilization plant — per-MWh rate is dominated by startup/standby emissions; not directly comparable to baseload averages.
NOx
33 lb/MWh
SO₂
0.040 lb/MWh
CH₄
0.027 lb/MWh
N₂O
0.003 lb/MWh
Capacity Factor
1.0%
Annual Net Gen
0 GWh
CO₂eq
1453 lb/MWh
Subregion
RFC East
2019
$1,078/kW
Est. Construction Cost
Total estimated cost: $3.4M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Somerville Substation · 230 kV
Substation Distance
2.387 km
Operator
PSE&G
Coord Source
OSM spatial
Market Position
ISO/RTO Market
PJM
LMP Node
SOMERVIL230 KV SOMERVSP
Pricing Hub
WESTERN HUB
Location Type
Generation Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about LabCorp EngineForward forecasts, scenario decomposition, and risk-decision tooling for this asset.