Search plants, projects, owners, and states
1276.8 MW Natural Gas planned in Sangamon, IL
1,276.8 MW
Nameplate Capacity
2
Generators
units
Natural Gas Fired Combined Cycle
Technology
Planned: —
Planned Operation
Coordinates
39.5788, -89.5798
County
Sangamon, IL
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Lincoln Land Energy Center LLC | Lincoln Land Energy Center | — |
| Owner(s) | Lincoln Land Energy Center LLC | Blackstone Group | — |
| Status | Planned | — | — |
The Lincoln Land Energy Center is a 1276.8 MW natural gas-fired combined cycle power plant located in Sangamon County, Illinois. It is owned by the Blackstone Group and operated by Lincoln Land Energy Center LLC. The plant consists of two generators utilizing combined cycle technology. It ranks as the 4th largest power plant in Illinois out of 32 plants, and 97th nationally out of 945 plants.
The plant operates within the Midcontinent Independent Transmission System Operator (MISO) balancing authority, which falls under the Southeastern Electric Reliability Council (SERC) NERC region. Recent news articles indicate regulatory interest in the facility.
Generated from EIA, GEM, and public data sources
ISO/RTO
MISO
Market
ISO/RTO Member
NERC Region
SERC — SERC Reliability Corporation
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc.. (MISO)
Grid Voltage
345.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
No generation data available for this plant.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2023
$782/kW
Est. Construction Cost
Total estimated cost: $998.5M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Pawnee substation · 345 kV
Substation Distance
< 10 km
Coord Source
OSM spatial
Market Position
ISO/RTO Market
MISO
LMP Node
—
Pricing Hub
ILLINOIS.HUB
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about Lincoln Land Energy CenterForward forecasts, scenario decomposition, and risk-decision tooling for this asset.