Search plants, projects, owners, and states
352.8 MW Wind operating in Foard, TX
352.8 MW
Nameplate Capacity
1
Generators
unit
Onshore Wind Turbine
Technology
2019
Operating Since
Coordinates
33.9097, -99.7443
County
Foard, TX
Nearby Plants
Forward-looking, asset-specific exposure profile combining climate hazards, generation variability, and counterparty risk into a single decision-grade signal.
See the full risk decomposition + scenarios for this asset.
Request a demo →Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Foard City Wind, LLC | GE Renewable Energy | — |
| Owner(s) | Foard City Wind, LLC | Irradiant Partners; Innergex Renewable Energy | — |
| Status | Operating | operating | — |
GEM identifies the owner as Irradiant Partners; Innergex Renewable Energy
This entity is not yet in the GEM ownership database — chain unavailable.
Foard City Wind is a 352.8 MW wind power plant located in Foard County, Texas. The plant began operating in 2019 and is owned and operated by Foard City Wind, LLC. It consists of a single generator utilizing onshore wind turbine technology. The facility is connected to the Electric Reliability Council of Texas, Inc. (ERCOT) balancing authority.
The plant utilizes GE Wind GE2.5-127 wind turbines, with a rotor diameter of 127 meters and a hub height of 89 meters. In its most recent year of operation, Foard City Wind generated 1,138,381 MWh of electricity, achieving a capacity factor of 36.9%. The plant ranks as the 15th largest wind farm in Texas out of 200, and 50th nationally out of 734.
Generated from EIA, GEM, and public data sources
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
Electric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
345.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
119.1K MWh
Latest Month
1.1M MWh
Annual Generation
36.9%
Capacity Factor
2019
$1,166/kW
Est. Construction Cost
Total estimated cost: $411.4M
Market Position
ISO/RTO Market
ERCOT
LMP Node
EDITHCLA7A
Pricing Hub
HB_NORTH
Node Source
EIA-860 direct report
Last updated 2026-03-26