161.3 MW Wind operating in Isabella, MI
161.3 MW
Nameplate Capacity
1
Generators
unit
Onshore Wind Turbine
Technology
2019
Operating Since
Coordinates
43.4823, -84.6616
County
Isabella, MI
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | DTE Electric Company | DTE Electric | — |
| Owner(s) | DTE Electric Company | DTE Energy | — |
| Status | Operating | operating | — |
Pine River Wind Park is a 161.3 MW wind power facility located in Isabella County, Michigan. The plant, which began operating in 2019, utilizes a single generator consisting of multiple onshore wind turbines. The facility is owned and operated by DTE Electric Company, a subsidiary of DTE Energy. The wind turbines have a hub height of 90 meters and a rotor diameter of 116 meters, and were manufactured by GE Wind, model GE2.5-116.
Pine River Wind Park operates within the Midcontinent Independent Transmission System Operator (MISO) balancing authority and the RFC NERC region. In its latest year of reported generation, the plant produced 380,627 MWh, achieving a capacity factor of 26.9%. The plant is ranked as the 9th largest wind farm in Michigan out of 19, and 446th nationally out of 734. The installed cost of the facility was $1670.96 per kW, according to FERC data.
Generated from EIA, GEM, and public data sources
ISO/RTO
MISO
Market
ISO/RTO Member
NERC Region
RFC
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc.. (MISO)
Grid Voltage
138.0 kV
Regulatory Status
RE — Regulated
Entity Type
Investor-Owned Utility
Sector
Electric Utility
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
46.6K MWh
Latest Month
380.6K MWh
Annual Generation
26.9%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
Wind · DTE Electric Company · Data from 2019–2024
$1,556/kW
Installed Cost
$6254.0/MWh
Operating Cost
Annual Capital & Operating Expenses
Cumulative Installed Cost
Per-Unit Cost Trends
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Shepherd Substation · 46 kV
Substation Distance
0 km
Operator
Consumers Energy
Coord Source
OSM spatial
Market Position
ISO/RTO Market
MISO
LMP Node
CONS.PINERVR1
Pricing Hub
MICHIGAN.HUB
Location Type
Generation Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Pine River Wind ParkForward forecasts, scenario decomposition, and risk-decision tooling for this asset.