Search plants, projects, owners, and states
1053 MW Hydro operating in Fresno, CA
1,053 MW
Nameplate Capacity
3
Generators
units
Hydroelectric Pumped Storage
Technology
1984
Operating Since
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Pacific Gas & Electric Co. | Pacific Gas and Electric | Pacific Gas and Electric Company |
| Owner(s) | Pacific Gas & Electric Co. | PG&E | — |
| Status | Operating | operating | — |
The Helms Pumped Storage Plant is located 50 miles (80 km) east of Fresno, California, in the Sierra Nevada Mountain Range's Sierra National Forest. It is a power station that uses Helms Creek canyon on the North Fork of the Kings River for off-river water storage and the pumped-storage hydroelectric method to generate electricity. After being planned in the early 1970s, construction on the plant began in June 1977 and commercial operations began on 30 June 1984. It has an installed capacity of 1,212 MW and is owned by Pacific Gas and Electric Company.
Read more on WikipediaHelms Pumped Storage is a 1,053 MW hydroelectric pumped storage plant located in Fresno County, California. The plant, which began operating in 1984, is owned and operated by Pacific Gas & Electric (PG&E). It utilizes water as its primary fuel source and consists of three generators. The plant's installed cost was $902.28 per kW, according to FERC data.
Helms Pumped Storage operates within the California Independent System Operator (CAISO) balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. It is the second-largest of 42 hydroelectric plants in California and ranks as the 18th-largest among 194 pumped storage facilities nationally.
Generated from EIA, GEM, and public data sources
ISO/RTO
CAISO
Market
ISO/RTO Member
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
California Independent System Operator (CISO)
Grid Voltage
230.0 kV
Regulatory Status
RE — Regulated
Entity Type
Investor-Owned Utility
Sector
Electric Utility
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
41.4K MWh
Net Discharge
-425.7K MWh
Annual Net Energy
-4.6%
Capacity Factor
Positive values indicate net discharge (generation exceeds station load). Negative values indicate net charging. Pure battery storage plants are typically net negative due to round-trip efficiency losses.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
PACIFIC GAS AND ELECTRIC COMPANY · Data from 2015–2024
$1,401/kW
Installed Cost
$85.0/MWh
Operating Cost
Annual Capital & Operating Expenses
Cumulative Installed Cost
Per-Unit Cost Trends
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
CAISO
LMP Node
HELMS1_7_B1
Pricing Hub
TH_ZP26_GEN-APND
Location Type
Pricing Node
Node Source
EIA-860 direct report
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Helms Pumped StorageForward forecasts, scenario decomposition, and risk-decision tooling for this asset.
FERC issued Authorization for Continued Project Operation for Helms Pumped Storage (Federal Register doc 2026-09301).
sourceFERC published Final Environmental Assessment for Helms Pumped Storage license proceedings (Federal Register doc 2026-09299).
sourceSecond FERC Authorization for Continued Project Operation notice issued for Helms (Federal Register doc 2026-09297), likely covering a distinct license component.
source