Search plants, projects, owners, and states
427.2 MW Natural Gas operating in Galveston, TX
427.2 MW
Nameplate Capacity
6
Generators
units
Natural Gas Fired Combustion Turbine
Technology
2018
Operating Since
Coordinates
29.4921, -94.9842
County
Galveston, TX
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | PHR Holdings LLC | — | — |
| Owner(s) | PHR Holdings LLC | — | — |
| Status | Operating | — | — |
The Bacliff power plant, located in Galveston County, Texas, has a total capacity of 427.2 MW. The plant began operating in 2018 and is owned and operated by PHR Holdings LLC. It utilizes six natural gas-fired combustion turbine generators. The plant operates within the Electric Reliability Council of Texas (ERCOT) balancing authority and the TRE NERC region.
In its most recent year of operation, Bacliff generated 103,084 MWh of electricity, resulting in a capacity factor of 2.7%. The plant is ranked 94th out of 144 power plants in Texas and 531st out of 945 plants nationally. Recent news coverage of the plant has focused on hazards.
Generated from EIA, GEM, and public data sources
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
Electric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
138.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Historic generation and capacity factor for this asset — the foundation for forward forecasts on the InfraSure platform.
655 MWh
Latest Month
103.1K MWh
Annual Generation
2.7%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
CO₂ Intensity
1573 lb/MWh
NOx
0.957 lb/MWh
SO₂
0.008 lb/MWh
CH₄
0.029 lb/MWh
N₂O
0.003 lb/MWh
Capacity Factor
6.7%
Annual Net Gen
252 GWh
CO₂eq
1575 lb/MWh
Subregion
ERCOT All
2018
$837/kW
Est. Construction Cost
Total estimated cost: $357.6M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
P. H. Robinson Peaker Substation · 138 kV
Substation Distance
< 10 km
Operator
CenterPoint Energy
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ERCOT
LMP Node
BAC_BAC_CTG1
Pricing Hub
HB_HOUSTON
Node Source
EIA-860 direct report
Last updated 2026-03-14
View all 7 articlesForward forecasts, scenario decomposition, and risk-decision tooling for this asset.