Search plants, projects, owners, and states
3.2 MW Bio. Gas operating in Polk, WI
3.2 MW
Nameplate Capacity
2
Generators
units
Other Waste Biomass
Technology
2013
Operating Since
Coordinates
45.3903, -92.1625
County
Polk, WI
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Viresco Turtle Lake | — | — |
| Owner(s) | Viresco Turtle Lake | — | — |
| Status | Operating | — | — |
Viresco Turtle Lake is a 3.2 MW biomass power plant located in Polk County, Wisconsin. The plant began operating in 2013 and is owned and operated by Viresco Turtle Lake. The facility utilizes two generators powered by other waste biomass (OBG). It ranks as the second-largest of four biomass plants in Wisconsin, and 27th out of 74 nationally.
The plant operates within the Midcontinent Independent Transmission System Operator (MISO) balancing authority. In its most recent year of operation, Viresco Turtle Lake generated 7,850 MWh of electricity, achieving a capacity factor of 27.9%. The plant is located within the Midwest Reliability Organization (MRO) NERC region.
Generated from EIA, GEM, and public data sources
ISO/RTO
MISO
Market
ISO/RTO Member
NERC Region
MRO — Midwest Reliability Organization
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc.. (MISO)
Grid Voltage
12.47 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP CHP
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
626 MWh
Latest Month
7.8K MWh
Annual Generation
27.9%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
CO₂ Intensity
0 lb/MWh
NOx
27 lb/MWh
SO₂
0.038 lb/MWh
CH₄
0.014 lb/MWh
N₂O
0.001 lb/MWh
Capacity Factor
18.8%
Annual Net Gen
5 GWh
CO₂eq
0.742 lb/MWh
Subregion
MRO West
2013
$3,495/kW
Est. Construction Cost
Total estimated cost: $11.2M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
MISO
LMP Node
Midwest ISO
Pricing Hub
MICHIGAN.HUB
Alt. Hub / Zone
MINN.HUB
Node Source
EIA-860 direct report
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about Viresco Turtle LakeForward forecasts, scenario decomposition, and risk-decision tooling for this asset.