Search plants, projects, owners, and states
60.5 MW Natural Gas operating in Tulare, CA
60.5 MW
Nameplate Capacity
1
Generators
unit
Natural Gas Fired Combustion Turbine
Technology
2013
Operating Since
Coordinates
35.7909, -119.2945
County
Tulare, CA
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Wellhead Services, Inc | California Holdings Delano | — |
| Owner(s) | California Holdings Delano 2 LLC, California Holdings Delano LLC | W Power | — |
| Status | Operating | — | — |
Delano Energy Center is a 60.5 MW natural gas-fired power plant located in Tulare County, California. The plant began operating in 2013 and has one natural gas-fired combustion turbine generator. It is owned by W Power and operated by Wellhead Services, Inc. The plant is interconnected to the California Independent System Operator (CAISO) balancing authority within the Western Electricity Coordinating Council (WECC) NERC region.
In the most recent year with available data, Delano Energy Center generated 7,320 MWh of electricity, resulting in a capacity factor of 1.4%. The plant ranks 96th in size among California's 297 power plants and 1062nd nationally out of 1963 plants.
Generated from EIA, GEM, and public data sources
ISO/RTO
CAISO
Market
ISO/RTO Member
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
California Independent System Operator (CISO)
Grid Voltage
69.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
372 MWh
Latest Month
7.3K MWh
Annual Generation
1.4%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
CO₂ Intensity
1413 lb/MWh
Low-utilization plant — per-MWh rate is dominated by startup/standby emissions; not directly comparable to baseload averages.
NOx
0.097 lb/MWh
SO₂
0.002 lb/MWh
CH₄
0.027 lb/MWh
N₂O
0.003 lb/MWh
Capacity Factor
0.4%
Annual Net Gen
2 GWh
CO₂eq
1414 lb/MWh
Subregion
WECC California
2013
$965/kW
Est. Construction Cost
Total estimated cost: $58.4M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
CAISO
LMP Node
VESTAL_6_N020
Pricing Hub
TH_SP15_GEN-APND
Alt. Hub / Zone
TH_ZP26_GEN-APND
Location Type
Pricing Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about Delano Energy CenterForward forecasts, scenario decomposition, and risk-decision tooling for this asset.