8.9 MW Natural Gas operating in Imperial, CA
8.9 MW
Nameplate Capacity
1
Generators
unit
Natural Gas Steam Turbine
Technology
1948
Operating Since
Coordinates
32.9111, -115.5681
County
Imperial, CA
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
Request a demo →| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Spreckels Sugar Company | — | — |
| Owner(s) | Spreckels Sugar Company | — | — |
| Status | Operating | — | — |
The Spreckels Sugar Company plant, located in Imperial County, California, is a natural gas-fired power plant with a total capacity of 8.9 MW. Operated by Spreckels Sugar Company, the plant began operations in 1948 and consists of a single natural gas steam turbine generator. The plant operates within the Imperial Irrigation District balancing authority and is part of the Western Electricity Coordinating Council (WECC) NERC region.
In the most recent year with available data, the Spreckels Sugar Company plant generated 19,860 MWh of electricity, achieving a capacity factor of 25.4%. In terms of size, the plant is ranked 185th out of 297 power plants in California and 1466th out of 1963 plants nationally.
Generated from EIA, GEM, and public data sources
Grid Region
California (non-ISO)
Market
Bilateral Market
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
1.8K MWh
Latest Month
19.9K MWh
Annual Generation
25.4%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
Request a demo →CO₂ Intensity
653 lb/MWh
NOx
0.917 lb/MWh
SO₂
2013
$965/kW
Est. Construction Cost
Total estimated cost: $8.6M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Request a demo →This plant is in a bilateral market territory without organized wholesale pricing. Nodal pricing data is not available.
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about Spreckels Sugar CompanyForward forecasts, scenario decomposition, and risk-decision tooling for this asset.
Request a demoImperial Irrigation District (IID)
Grid Voltage
4.16 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Industrial
Sector
Industrial CHP
0.003 lb/MWh
CH₄
0.012 lb/MWh
N₂O
0.001 lb/MWh
Capacity Factor
20.3%
Annual Net Gen
16 GWh
CO₂eq
653 lb/MWh
Subregion