150 MW Wind operating in Tom Green, TX
150 MW
Nameplate Capacity
1
Generators
unit
Onshore Wind Turbine
Technology
2009
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
31.0854, -100.6788
Reference point reported to EIA.
County
Tom Green, TX
Nearby Plants
The available map data does not yet establish a route from this plant to the grid.
No suitable mapped facility was found in the area searched. Missing map data does not mean the plant has no grid connection.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
Owner data does not fully agree across sources.
Sources can describe different roles or reporting dates. The source-specific values below are retained for comparison.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Langford Wind Power LLC | Clearway Energy Group | — |
| Owner(s) | Langford Wind Power LLC | Clearway Energy | — |
| Status | Operating | retired | — |
Summary generated Mar 21, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
Langford Wind Power is a 150 MW wind power plant located in Tom Green County, Texas. The plant began operating in 2009 and is owned by Clearway Energy and operated by Langford Wind Power LLC. The facility utilizes a single generator consisting of onshore wind turbines. The plant connects to the Electric Reliability Council of Texas, Inc. (ERCOT) balancing authority.
The plant's wind turbines have a hub height of 80 meters and a rotor diameter of 91 meters. The turbines were manufactured by GE Wind, and the model is GE1.6-91. In its latest year of reported generation, Langford Wind Power produced 572,942 MWh, achieving a capacity factor of 43.5%. Langford Wind Power ranks as the 157th largest wind plant in Texas out of 200, and 489th nationally out of 734.
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
Electric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
138.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Connection evidence
Connection unresolved
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
48.9K MWh
Latest Month
572.9K MWh
Annual Generation
43.5%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2013
$1,895/kW
Est. Construction Cost
Total estimated cost: $284.3M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Langford Wind Substation · 138 kV
Substation Distance
0 km
Operator
NRG Energy
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ERCOT
LMP Node
LGD_LANGFORD
Pricing Hub
HB_WEST
Alt. Hub / Zone
LZ_WEST
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-04-09
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this asset.