Search plants, projects, owners, and states
52.8 MW Wind operating in Erath, TX
52.8 MW
Nameplate Capacity
1
Generators
unit
Onshore Wind Turbine
Technology
2008
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
32.3387, -98.4761
Reference point reported to EIA.
County
Erath, TX
Nearby Plants
The starting substation is nearby, but its connection to this plant is unconfirmed.
1 mapped line section connects the two facilities over 7.317 km. At least one endpoint uses a nearby spatial match.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Silver Star I Power Partners LLC | EDF Renewables | — |
| Owner(s) | Texas Wind Repower HoldCo, L.P. c/o Concord Infrastructure Investments, LLC, UBS Asset Management (Americas) Inc | Ares Management | — |
| Status | Operating | retired | — |
Summary generated Mar 22, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
The Silver Star I Wind Power Project is a 52.8 MW wind farm located in Erath County, Texas. The plant began operating in 2008 and is owned by Ares Management, with Silver Star I Power Partners LLC as the operator. The facility utilizes a single onshore wind turbine generator. The plant's location places it within the Electric Reliability Council of Texas (ERCOT) balancing authority and the Texas Reliability Entity (TRE) NERC region.
The wind farm's turbine is a Vestas V110-2.0 model, featuring a rotor diameter of 110 meters and a hub height of 80 meters. In the most recent year of data, the plant generated 200,544 MWh of electricity, achieving a capacity factor of 43.3%. Silver Star I ranks as the 223rd largest wind farm in Texas out of 245, and 915th nationally out of 1424.
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
Electric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
138.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Connection evidence
Mapped route candidate
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
16.6K MWh
Latest Month
200.5K MWh
Annual Generation
43.3%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2013
$1,895/kW
Est. Construction Cost
Total estimated cost: $100.1M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Silver Star Wind Substation · 138 kV
Substation Distance
0 km
Operator
BP
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ERCOT
LMP Node
FLTCK_SSI
Pricing Hub
HB_NORTH
Alt. Hub / Zone
LZ_NORTH
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
Silver Star repower
Comparative analysis covering fleet scale, performance trends, and growth pipeline.
Silver Star I Wind Power Project
Data-driven briefing on Silver Star I Wind Power Project — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this asset.