Search plants, projects, owners, and states
242 MW Natural Gas operating in Fayette, TX
242 MW
Nameplate Capacity
4
Generators
units
Natural Gas Fired Combustion Turbine
Technology
2010
Operating Since
Coordinates
30.0250, -96.9935
County
Fayette, TX
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Lower Colorado River Authority | Lower Colorado River Authority | — |
| Owner(s) | Lower Colorado River Authority | Lower Colorado River Authority | — |
| Status | Operating | — | — |
Winchester Power Park is a 242 MW natural gas-fired power plant located in Fayette County, Texas. The plant began operating in 2010 and consists of four natural gas-fired combustion turbine generators. It is owned and operated by the Lower Colorado River Authority.
The plant operates within the Electric Reliability Council of Texas (ERCOT) balancing authority. In the most recent year with available data, Winchester Power Park generated 51,545 MWh of electricity, equivalent to a capacity factor of 2.4%. Winchester Power Park is ranked as the 111th largest power plant in Texas out of 144, and 707th nationally out of 945.
Generated from EIA, GEM, and public data sources
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
Electric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
138.0 kV
Regulatory Status
RE — Regulated
Entity Type
Political Subdivision
Sector
Electric Utility
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
2.0K MWh
Latest Month
51.5K MWh
Annual Generation
2.4%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
CO₂ Intensity
1167 lb/MWh
NOx
0.100 lb/MWh
SO₂
0.006 lb/MWh
CH₄
0.024 lb/MWh
N₂O
0.002 lb/MWh
Capacity Factor
4.1%
Annual Net Gen
86 GWh
CO₂eq
1168 lb/MWh
Subregion
ERCOT All
2013
$965/kW
Est. Construction Cost
Total estimated cost: $233.6M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Winchester Power Park Substation · 138 kV
Substation Distance
0 km
Operator
Lower Colorado River Authority
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ERCOT
LMP Node
WIPOPA_1_2
Pricing Hub
HB_SOUTH
Alt. Hub / Zone
LZ_SOUTH
Location Type
Resource Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
Forward forecasts, scenario decomposition, and risk-decision tooling for this asset.