38.2 MW All Other (32 MW) + Natural Gas Fired Combustion Turbine (6 MW) operating in Salt Lake, UT
38.2 MW
Nameplate Capacity
2
Generators
units
Hybrid (2)
Technology
All Other + Natural Gas Fired Combustion Turbine
1995
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
40.7115, -112.1231
Reference point calculated from the selected footprint.
Mapped site outline
Site outline mapped in OpenStreetMap. It is not a surveyed or legal boundary.
County
Salt Lake, UT
Nearby Plants
Voltage information is incomplete along this route; the electrical connection remains unconfirmed.
1 mapped line section connects the two facilities over 0.287 km. The line reaches both facility footprints in the source data.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Kennecott Utah Copper | Kennecott Utah Copper | — |
| Owner(s) | Kennecott Utah Copper | Rio Tinto | — |
| Status | Operating | — | — |
Summary generated Mar 22, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
The Kennecott Power Plant is a 38.2 MW natural gas-fired power plant located in Salt Lake County, Utah. The plant began operating in 1995 and consists of two generators utilizing natural gas-fired combustion turbine technology. It is owned by Rio Tinto, a company based in the United Kingdom, and operated by Kennecott Utah Copper. The plant is a hybrid facility.
In the most recent year of reported data, the Kennecott Power Plant generated 152,264 MWh of electricity, achieving a capacity factor of 45.6%. The plant operates within the PacifiCorp - East balancing authority, which is part of the Western Electricity Coordinating Council (WECC) NERC region. Kennecott Power Plant ranks 9th out of 24 power plants in Utah and 1198th out of 1963 plants nationally.
Grid Region
Mountain West
Market
WEIM Participant
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
PacifiCorp - East (PACE)
Grid Voltage
138.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Industrial
Sector
Industrial CHP
Connection evidence
Mapped route candidate
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
20.0K MWh
Latest Month
152.3K MWh
Annual Generation
45.6%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
CO₂ Intensity
219 lb/MWh
NOx
0.600 lb/MWh
SO₂
0.006 lb/MWh
CH₄
0.004 lb/MWh
N₂O
0.000 lb/MWh
Capacity Factor
19.0%
Annual Net Gen
64 GWh
CO₂eq
219 lb/MWh
Subregion
WECC Northwest
2013
$965/kW
Est. Construction Cost
Total estimated cost: $36.9M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
This plant's balancing authority participates in CAISO's Western Energy Imbalance Market (WEIM). Direct nodal pricing data is not yet available.
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-03-14
View all 10 articlesForward forecasts, scenario decomposition, and risk-decision tooling for this asset.