678.3 MW Natural Gas operating in Contra Costa, CA
678.3 MW
Nameplate Capacity
3
Generators
units
Natural Gas Fired Combined Cycle
Technology
2001
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
38.0301, -121.8731
Reference point calculated from the selected footprint.
Mapped site outline
Site outline mapped in OpenStreetMap. It is not a surveyed or legal boundary.
County
Contra Costa, CA
Nearby Plants
An endpoint uses a short spatial match; the actual terminal connection remains unconfirmed.
2 mapped line sections connect the two facilities over 0.369 km. At least one endpoint uses a nearby spatial match.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Reverse views of the same physical route are grouped in the route selector. All source records are retained.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Los Medanos Energy Center LLC | Los Medanos Energy Center | — |
| Owner(s) | Los Medanos Energy Center LLC | Constellation Energy | — |
| Status | Operating | — | — |
Summary generated Mar 21, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
Los Medanos Energy Center is a 678.3 MW natural gas-fired combined cycle power plant located in Contra Costa County, California. The plant began operating in 2001 and consists of 3 generators. It is owned by Constellation Energy and operated by Los Medanos Energy Center LLC. The plant is located within the California Independent System Operator (CAISO) balancing authority and the Western Electricity Coordinating Council (WECC) NERC region.
In the most recent year with available data, Los Medanos Energy Center generated 2,485,539 MWh of electricity, achieving a capacity factor of 41.9%. The plant is ranked as the 18th largest in California out of 76 power plants, and 336th nationally out of 945 plants.
ISO/RTO
CAISO
Market
ISO/RTO Member
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
California Independent System Operator (CISO)
Grid Voltage
115.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP CHP
Connection evidence
Mapped route candidate
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
348.9K MWh
Latest Month
2.5M MWh
Annual Generation
41.9%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
CO₂ Intensity
790 lb/MWh
NOx
0.048 lb/MWh
SO₂
0.004 lb/MWh
CH₄
0.014 lb/MWh
N₂O
0.001 lb/MWh
Capacity Factor
51.5%
Annual Net Gen
3062 GWh
CO₂eq
791 lb/MWh
Subregion
WECC California
2013
$965/kW
Est. Construction Cost
Total estimated cost: $654.6M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
CAISO
LMP Node
POD_LMEC_1_PL1X3-APND
Pricing Hub
TH_NP15_GEN-APND
Node Source
EIA-860 direct report
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
Forward forecasts, scenario decomposition, and risk-decision tooling for this asset.