Search plants, projects, owners, and states
170.8 MW Hydro operating in Tuolumne, CA
170.8 MW
Nameplate Capacity
4
Generators
units
Conventional Hydroelectric
Technology
1971
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
37.6960, -120.4201
Reference point calculated from the selected footprint.
Mapped site outline
Site outline mapped in OpenStreetMap. It is not a surveyed or legal boundary.
County
Tuolumne, CA
Nearby Plants
The starting substation is nearby, but its connection to this plant is unconfirmed.
3 mapped line sections connect the two facilities over 33.844 km. At least one endpoint uses a nearby spatial match.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Turlock Irrigation District | Turlock Irrigation District | — |
| Owner(s) | Modesto Irrigation District, Turlock Irrigation District | Modesto Irrigation District | — |
| Status | Operating | operating | — |
New Don Pedro Dam, often known simply as Don Pedro Dam, is an earthen embankment dam across the Tuolumne River, about 2 miles (3.2 km) northeast of La Grange, in Tuolumne County, California. The dam was completed in 1971, after four years of construction, to replace the 1924 concrete-arch Don Pedro Dam.
Read more on WikipediaSummary generated Mar 21, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
The Don Pedro Hydroelectric Plant is located in Tuolumne County, California. The plant has a total capacity of 170.8 MW across 4 generators, utilizing conventional hydroelectric technology and water (WAT) as its primary fuel source. It began operating in 1971. The plant is owned by Modesto Irrigation District and operated by Turlock Irrigation District, which also serves as the balancing authority. Don Pedro operates within the Western Electricity Coordinating Council (WECC) NERC region.
In the most recent year with available data, the plant generated 279,866 MWh of electricity, resulting in a capacity factor of 18.6%. Don Pedro ranks as the 19th largest hydroelectric plant out of 42 in California, and 113th out of 194 nationally.
Grid Region
California (non-ISO)
Market
WEIM Participant
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
Turlock Irrigation District (TIDC)
Grid Voltage
69.0 kV
Regulatory Status
RE — Regulated
Entity Type
Political Subdivision
Sector
Electric Utility
Connection evidence
Mapped route candidate
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
24.1K MWh
Latest Month
279.9K MWh
Annual Generation
18.6%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2013
$2,294/kW
Est. Construction Cost
Total estimated cost: $391.9M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
This plant's balancing authority participates in CAISO's Western Energy Imbalance Market (WEIM). Direct nodal pricing data is not yet available.
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-03-26
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this asset.