Search plants, projects, owners, and states
950 MW Hydro operating in Grant, WA
950 MW
Nameplate Capacity
10
Generators
units
Conventional Hydroelectric
Technology
1959
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
46.6452, -119.9083
Reference point calculated from the selected footprint.
Mapped site outline
Site outline mapped in OpenStreetMap. It is not a surveyed or legal boundary.
County
Grant, WA
Nearby Plants
The route starts at a transmission substation on the mapped site; its link to the plant’s generation equipment is unconfirmed.
1 mapped line section connects the two facilities over 6.069 km. The line reaches both facility footprints in the source data.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
Owner data does not fully agree across sources.
Sources can describe different roles or reporting dates. The source-specific values below are retained for comparison.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | PUD No 2 of Grant County - (WA) | Grant County Public Utility District | — |
| Owner(s) | PUD No 2 of Grant County - (WA) | Grant County Public Utility District | — |
| Status | Operating | operating | — |
Priest Rapids Dam is a hydroelectric, concrete gravity dam; located on the Columbia River, between the Yakima Firing Range and the Hanford Nuclear Reservation, and bridges Yakima County and Grant County, in the U.S. state of Washington. The dam is 24 miles south of the town of Vantage, and 47 miles northwest of the city of Richland. It is located at mile marker 397.1 from the mouth of the Columbia. It is owned by the Grant County Public Utility District (PUD). Priest Rapids, for which the dam was named, are now submerged beneath the dam's reservoir.
Read more on WikipediaSummary generated Mar 21, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
Priest Rapids is a 950 MW hydroelectric power plant located in Grant County, Washington. The plant began operating in 1959 and utilizes conventional hydroelectric technology. It consists of 10 generators and is owned and operated by PUD No 2 of Grant County. The primary fuel source for electricity generation is water (WAT).
In the most recent year of available data, Priest Rapids generated 4,164,860 MWh of electricity, achieving a capacity factor of 50.0%. The plant is connected to the grid within the Bonneville Power Administration balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. Priest Rapids ranks as the 6th largest power plant out of 23 in Washington state, and 25th out of 194 hydroelectric plants nationally.
Grid Region
Pacific Northwest
Market
WEIM Participant
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
Bonneville Power Administration (BPAT)
Grid Voltage
230.0 kV
Regulatory Status
RE — Regulated
Entity Type
Political Subdivision
Sector
Electric Utility
Connection evidence
Mapped route candidate
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
504.6K MWh
Latest Month
4.2M MWh
Annual Generation
50.0%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2013
$2,294/kW
Est. Construction Cost
Total estimated cost: $2.2B
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
This plant's balancing authority participates in CAISO's Western Energy Imbalance Market (WEIM). Direct nodal pricing data is not yet available.
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-04-19
View all articlesIMPA Washington Solar Park
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
IMPA Washington Solar Park 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Hydro Plant
Data tables and metrics from the InfraSure database.
Priest Rapids
Data-driven briefing on Priest Rapids — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this asset.
Mineral oil spilled from Priest Rapids Dam into the Columbia River; state and federal agencies launched an investigation and cleanup concluded by late December 2025.