96.3 MW Natural Gas Fired Combustion Turbine (47 MW) + Natural Gas Steam Turbine (49 MW) operating in Chautauqua, NY
96.3 MW
Nameplate Capacity
3
Generators
units
Hybrid (2)
Technology
Natural Gas Fired Combustion Turbine + Natural Gas Steam Turbine
1951
Operating Since
Coordinates
42.0936, -79.2475
County
Chautauqua, NY
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Jamestown Board of Public Util | — | — |
| Owner(s) | Jamestown Board of Public Util | — | — |
| Status | Operating | — | — |
The S A Carlson plant is a 96.3 MW hybrid power plant located in Chautauqua County, New York. It began operating in 1951 and is owned and operated by Jamestown Board of Public Utilities. The plant utilizes natural gas as its primary fuel source and incorporates both natural gas-fired combustion turbine and natural gas steam turbine technologies across its three generators.
The plant operates within the New York Independent System Operator (NYISO) balancing authority and the Northeast Power Coordinating Council (NPCC) NERC region. In the most recent year with available data, the S A Carlson plant generated 33,501 MWh of electricity, achieving a capacity factor of 3.9%. It is ranked as the 39th largest power plant in New York out of 102 plants, and nationally it is ranked 955th out of 1963 plants.
Generated from EIA, GEM, and public data sources
ISO/RTO
NYISO
Market
ISO/RTO Member
NERC Region
NPCC — Northeast Power Coordinating Council
Balancing Authority
New York Independent System Operator (NYIS)
Grid Voltage
15.0 kV
Regulatory Status
RE — Regulated
Entity Type
Municipal
Sector
Electric Utility
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
2.9K MWh
Latest Month
33.5K MWh
Annual Generation
3.9%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
CO₂ Intensity
1112 lb/MWh
NOx
1 lb/MWh
SO₂
0.006 lb/MWh
CH₄
0.021 lb/MWh
N₂O
0.002 lb/MWh
Capacity Factor
6.2%
Annual Net Gen
52 GWh
CO₂eq
1113 lb/MWh
Subregion
NPCC Upstate NY
2013
$965/kW
Est. Construction Cost
Total estimated cost: $92.9M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
NYISO
LMP Node
—
Pricing Hub
WEST
Node Source
Plant coordinates only
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about S A CarlsonForward forecasts, scenario decomposition, and risk-decision tooling for this asset.