Search plants, projects, owners, and states
21.6 MW Hydro operating in Lincoln, NE
21.6 MW
Nameplate Capacity
2
Generators
units
Conventional Hydroelectric
Technology
1941
Operating Since
Coordinates
40.9593, -100.3979
County
Lincoln, NE
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Central Nebraska Pub P&I Dist | — | — |
| Owner(s) | Central Nebraska Pub P&I Dist | — | — |
| Status | Operating | — | — |
The Jeffrey Hydroelectric Plant, identified by plant code 2227, is located in Lincoln County, Nebraska. The plant has a total capacity of 21.6 MW derived from two conventional hydroelectric generators. It began operating in 1941 and is owned and operated by Central Nebraska Public Power and Irrigation District. The plant's primary fuel source is water (WAT).
Jeffrey operates within the Southwest Power Pool (SPP) balancing authority and the Midwest Reliability Organization (MRO) NERC region. In the state of Nebraska, Jeffrey ranks as the 6th largest of 9 hydroelectric plants. Nationally, it ranks 474th out of 1464 similar facilities. The plant's latest annual generation was 86,277 MWh, resulting in a capacity factor of 45.5%.
Generated from EIA, GEM, and public data sources
ISO/RTO
SPP
Market
ISO/RTO Member
NERC Region
MRO — Midwest Reliability Organization
Balancing Authority
Southwest Power Pool (SWPP)
Grid Voltage
115.0 kV
Regulatory Status
RE — Regulated
Entity Type
Political Subdivision
Sector
Electric Utility
Historic generation and capacity factor for this asset — the foundation for forward forecasts on the InfraSure platform.
4.1K MWh
Latest Month
86.3K MWh
Annual Generation
45.5%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2013
$2,294/kW
Est. Construction Cost
Total estimated cost: $49.6M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
SPP
LMP Node
NPPDJEFFREYUN1
Pricing Hub
SPP North Hub
Node Source
EIA-860 direct report
Last updated 2026-03-14
View all articlesNo Ask reports yet for this entity.
Ask about JeffreyForward forecasts, scenario decomposition, and risk-decision tooling for this asset.