234.7 MW Natural Gas Fired Combined Cycle (213 MW) + Petroleum Liquids (21 MW) operating in Middlesex, MA
234.7 MW
Nameplate Capacity
3
Generators
units
Hybrid (2)
Technology
Natural Gas Fired Combined Cycle + Petroleum Liquids
1958
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
42.3633, -71.0802
Reference point calculated from the selected footprint.
Mapped site outline
Site outline mapped in OpenStreetMap. It is not a surveyed or legal boundary.
County
Middlesex, MA
Nearby Plants
An endpoint uses a short spatial match; the actual terminal connection remains unconfirmed.
1 mapped line section connects the two facilities over 4.310 km. At least one endpoint uses a nearby spatial match.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Reverse views of the same physical route are grouped in the route selector. All source records are retained.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Kendall Green Energy, LLC | Kendall Green Energy | — |
| Owner(s) | Kendall Green Energy, LLC | Antin Infrastructure Partners | — |
| Status | Operating | — | — |
The Kendall facility is an energy facility owned by Vicinity Energy that produces steam and electricity to the cities of Boston and Cambridge. Owned by GenOn Energy in 2012, in 2013 Veolia Energy North America purchased the plant from NRG Energy. In 2020, Antin Infrastructure Partners acquired Veolia Energy North America and renamed it Vicinity Energy.
Read more on WikipediaSummary generated Mar 21, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
Kendall Square Station is a 234.7 MW hybrid power plant located in Middlesex County, Massachusetts. The plant began operating in 1958 and is owned by Antin Infrastructure Partners, a French company. The operator is Kendall Green Energy, LLC. The facility utilizes both natural gas and petroleum liquids as fuel, employing natural gas-fired combined cycle technology. It consists of 3 generators.
The plant operates within the ISO New England Inc. balancing authority and the NPCC NERC region. In the state of Massachusetts, Kendall Square Station ranks as the 11th largest out of 15 power plants. Nationally, it is ranked 714 out of 945. The latest annual generation data indicates an output of 1,535,175 MWh, resulting in a capacity factor of 74.6%.
ISO/RTO
ISO-NE
Market
ISO/RTO Member
NERC Region
NPCC — Northeast Power Coordinating Council
Balancing Authority
ISO New England Inc. (ISNE)
Grid Voltage
115.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP CHP
Connection evidence
Mapped route candidate
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
141.4K MWh
Latest Month
1.5M MWh
Annual Generation
74.6%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
CO₂ Intensity
683 lb/MWh
NOx
0.047 lb/MWh
SO₂
0.003 lb/MWh
CH₄
0.013 lb/MWh
N₂O
0.001 lb/MWh
Capacity Factor
74.1%
Annual Net Gen
1524 GWh
CO₂eq
683 lb/MWh
Subregion
NPCC New England
2013
$965/kW
Est. Construction Cost
Total estimated cost: $226.5M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
East Cambridge Substation · 115 kV
Substation Distance
< 10 km
Operator
Eversource
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ISO-NE
LMP Node
1672
Pricing Hub
.H.INTERNAL_HUB
Node Source
EIA-860 direct report
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
Oxy Renewable Energy queue pipeline — 1 projects by technology and status
Summary analysis with parallel narrative sections and visualizations.
Massachusetts growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ISO New England
Summary analysis with parallel narrative sections and visualizations.
Oxy Renewable Energy queue pipeline — 1 projects by technology and status
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this asset.