Search plants, projects, owners, and states
5.4 MW Hydro operating in Grayson, VA
5.4 MW
Nameplate Capacity
4
Generators
units
Conventional Hydroelectric
Technology
1933
Operating Since
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Central Rivers Power US, LLC | — | — |
| Owner(s) | Central Rivers Power US, LLC | — | — |
| Status | Operating | — | — |
The Fries Hydroelectric Project is a 5.4 MW hydroelectric power plant located in Grayson County, Virginia. The plant began operating in 1933 and consists of four generators utilizing conventional hydroelectric technology. It is owned and operated by Central Rivers Power US, LLC.
The Fries plant operates within the PJM Interconnection, LLC balancing authority and the RFC NERC region. It is the 13th largest of 25 hydroelectric plants in Virginia, and ranks 857th out of 1464 hydroelectric plants nationally. The plant's primary fuel source is water (WAT).
Generated from EIA, GEM, and public data sources
ISO/RTO
PJM
Market
ISO/RTO Member
NERC Region
RFC
Balancing Authority
PJM Interconnection, LLC (PJM)
Grid Voltage
13.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
0 MWh
Latest Month
0 MWh
Annual Generation
0.0%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2013
$2,294/kW
Est. Construction Cost
Total estimated cost: $12.4M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Fries Substation · 69 kV
Substation Distance
0.04 km
Operator
Appalachian Power Company
Coord Source
OSM spatial
Market Position
ISO/RTO Market
PJM
LMP Node
FRIES 12 KV FRIESHYD
Pricing Hub
DOMINION HUB
Location Type
Generation Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about Fries Hydroelectric ProjectForward forecasts, scenario decomposition, and risk-decision tooling for this asset.