The read
The decision in four lines
- 01“Behind the meter” identifies one boundary. It does not define the service bargain.
- 02A site may withdraw less from the grid and still depend on it for backup, controls, reliability support, and settlement.
- 03Some PJM interconnection options are usable now; the three new transmission services are not yet generally available.
- 04Before accepting “powered” or “ready,” ask which documents prove the configuration, rights, effective rule, controls, and current load.
The label is not the decision
“Behind the meter” sounds like an answer to interconnection delay, network upgrades, and grid cost. It is not the answer. It is the first line of a diligence request.
A data center can sit beside a generator, take little or nothing from the wider grid during ordinary operations, and still depend on the system for backup service, controls, reliability support, and settlement. Physical distance is visible. The service bargain is documentary.
The meter tells you where to start reading. It does not tell you where the obligations stop.
Adjacency is visible. Service is not.
Figure 01
The physical proximity is real. So is the temptation to let the photograph answer questions it cannot. This view of the Susquehanna plant record does not reveal the meter boundary, current service, tariff enrollment, withdrawal right, or direction of power flow. Those facts have to be proved separately.
This distinction matters now because PJM's framework is moving on different clocks. Selected interconnection options are already effective. The three transmission-service paths most “limited grid use” claims rely on have been directed and materially shaped, but they do not yet have an approved effective date. At the same time, FERC has opened six tailored proceedings asking organized markets to confront large-load integration.
Five questions define the interface
A useful analysis does not begin by choosing between “behind” and “in front” of the meter. It begins by resolving five linked questions:
- Physical configuration — Where are the load, generator, meter, and point of interconnection? Is the campus fully islanded, synchronized behind a shared point, or served through a front-of-meter path?
- Withdrawal right — How much may the load take from the grid, under which conditions, and with what firmness? Contract demand is not gross load, current demand, or unlimited backup.
- Injection right — How much may the generator inject, and which studies or interconnection rights change when some output serves a nearby load?
- Operational duty — What metering, telemetry, controls, protection, curtailment, load-shed, and notice obligations govern the interface?
- Cost duty — Which transmission, ancillary-service, upgrade, administrative, and retail charges apply under the effective rules?
Three configurations. Three different bargains.
Figure 02Configuration 01
Fully islanded
The grid connection is physically absent or open.
- Prove with
- One-line diagram, protection design, operating record
- Still cannot claim
- Does not prove the campus has resilient backup.
Configuration 02
Co-located / limited withdrawal
The site remains connected, but its withdrawal right is bounded.
- Prove with
- Meter diagram, service agreement, tariff, controls
- Still cannot claim
- Does not mean zero grid duty or unlimited backup.
Configuration 03
Front of meter
Generation and load use utility and wholesale service paths.
- Prove with
- PPA, retail supply, delivery and transmission records
- Still cannot claim
- Does not prove the campus is taking a specific new PJM product.
These are configurations, not rankings. Fully islanded can remove a transmission-service relationship only by giving up synchronized grid service. A co-located arrangement may limit withdrawals, but its contract and controls define the boundary. A front-of-meter structure can use familiar utility and wholesale paths while adding parties and obligations. The right answer depends on the service design and the evidence behind it—not on which label sounds more independent.
The limited-withdrawal bargain has teeth
The new service design is not simply a cheaper or softer version of ordinary service. It exchanges a smaller or less-firm withdrawal right for stronger operational limits.
In its June order, FERC directed a framework under which PJM may terminate the affected transmission-service agreement after a second failure to follow a curtailment or load-shed instruction. A first misoperation of required control technology or protection systems can lead to a suspension of up to 120 days; a second can lead to termination.
Those are replacement-rate directions awaiting compliant tariff implementation—not proof that any named customer is subject to them today. But they expose the cost of a loose claim. A mistaken assumption about firmness, controls, or curtailment can reach the service agreement itself.
What can change—and what cannot be assumed
What can move—and what still needs proof
Figure 03Can change
Net quantity withdrawn
Cannot assume
The site has no grid dependence
Can change
Firm or non-firm service requested
Cannot assume
Backup is unlimited or continuously guaranteed
Can change
Facilities studied for service
Cannot assume
Studies, upgrades, or charges disappear
Can change
Exposure to curtailment and control duties
Cannot assume
A powered claim proves current operating load
Can change
Commercial path among generator, customer, utility, and PJM
Cannot assume
One configuration is always cheaper, faster, or safer
Co-location can change the net quantity withdrawn from the wider system, the firm or non-firm service requested, the facilities studied for that service, exposure to curtailment, and the commercial path among generator, customer, utility, and PJM.
It does not automatically remove grid dependence, grant unlimited backup, eliminate studies or charges, establish current load, or prove that one architecture is universally better. FERC's June order is especially clear on the cost edge: zero net withdrawal does not erase the regulation and black-start benefits a co-located load may receive, and the tariff must address recovery of those costs.
The same precision applies to Non-Firm Contract Demand. Eligible customers must be allowed to request it on an everyday basis during normal operations when transmission capacity is available. It remains non-firm, as-available, and curtailable. “Requestable every day” is not “continuously guaranteed.”
Susquehanna: the regulator already ran the evidence test
In 2024, PJM filed an amended interconnection service agreement seeking to increase the co-located-load treatment at Susquehanna from 300 MW to 480 MW. FERC rejected the agreement—not as a general verdict against nuclear-powered data centers, but because PJM did not meet the high burden for non-conforming provisions. The record did not show that those deviations from the pro forma agreement were necessary, and it relied in part on guidance that was not in the approved tariff.
That is the central lesson in miniature: the label could not substitute for the proof objects.
The campus changed before the generic rule settled
Figure 04Track 1
Campus record
What happened to the named Susquehanna–AWS arrangement
Nov 2024
480 MW amendment rejected
FERC found the non-conforming provisions were not justified in the controlling record.
Jun 2025
Front-of-meter path disclosed
Talen described a three-party supply, transmission, and delivery structure.
Apr 2026
Transition reported
Talen's Q1 Form 10-Q says the revised front-of-meter PPA transition occurred.
Track 2
Generic PJM record
What happened to the rules that may govern other arrangements
Dec 2025
Replacement framework directed
FERC established the initial large-load and co-location architecture.
Apr 2026
Selected interconnection options effective
Below-nameplate requests and selected interconnection provisions were accepted.
Jun–Jul 2026
Transmission services still resolving
FERC reshaped the service design; PJM moved into compliance and stakeholder work.
The next move was not “outside the grid.” Talen's June 2025 disclosure described a three-party front-of-meter path: Susquehanna would sell power into PJM, Talen would act as Amazon's retail generation supplier, and PPL Electric Utilities would provide transmission and delivery after physical reconfiguration. Talen's Q1 2026 Form 10-Q later reported that the revised front-of-meter PPA transition occurred in April 2026.
The public 1,920 MW figure belongs to the PPA's contractual ramp through 2042. It is not current campus load, current withdrawal, or current energized capacity. Nor does the April transition prove that AWS is taking Interim NITS, Firm Contract Demand, or Non-Firm Contract Demand.
The interface did not disappear when the structure moved front-of-meter. It acquired more parties.
Three clocks, one framework
Read the framework on three clocks
Figure 05Clock 1
Usable now
Selected interconnection options
Includes below-nameplate study requests, provisional interconnection service, surplus interconnection service, and existing acceleration provisions within scope.
Clock 2
Directed, not generally available
Interim NITS, Firm Contract Demand, and Non-Firm Contract Demand
The architecture has been ordered and materially shaped, but the compliance path and service timing are still resolving.
Clock 3
Questions opened
Six tailored large-load proceedings
PJM, MISO, SPP, CAISO, ISO New England, and NYISO must respond; this is not one uniform national rule.
In effect since 16 April 2026. Read the accepted interconnection provisions. FERC accepted selected PJM interconnection provisions, including the ability to request service below generator nameplate and be studied at the requested level, provisional interconnection service, surplus interconnection service, and existing acceleration provisions. These are interconnection-side options a developer can use within the order's scope.
Directed, with no approved effective date. Read the June replacement-rate order. Interim NITS, Firm Contract Demand, and Non-Firm Contract Demand are the ordered transmission-service architecture. PJM proposed 1 June 2029. FERC found the support insufficient, required reconsideration, and asked whether interim and non-firm service could arrive sooner. An analyst may describe the directed structure; they may not present any of the three services as generally available today.
Newly opened across six markets. Read FERC's six-market action. On 18 June, FERC opened tailored proceedings for PJM, MISO, SPP, CAISO, ISO New England, and NYISO around shared large-load reform questions. They are not one national rule. PJM's co-location questions remain in the separate EL25-49 track, while its new EL26-67 proceeding focuses principally on large loads that are not co-located.
Collapsing those clocks into “the rule is live” or “the rule is pending” produces the wrong decision in both directions.
Six proof objects before believing a powered claim
The practical test is simple: turn the headline into a document request.
| Proof object | What it answers | What its absence blocks |
|---|---|---|
| One-line and meter diagram | Physical boundary and synchronization | Configuration claim |
| Generator interconnection agreement and study | Injection rights and modification path | Generator/grid-right claim |
| Load transmission or service agreement | Withdrawal quantity and firmness | Backup/service claim |
| Effective tariff and order version | Current rule and obligations | Applicability/effective claim |
| Telemetry, control, and curtailment specification | Operational limit and enforcement | Reliability/firmness claim |
| Current meter, service, and load record | Actual energized state and demand | “Operating at X MW” claim |
This is not paperwork for its own sake. The Susquehanna agreement failed its 2024 test because the required deviation was not established in the controlling record. In the current docket, confusing an order, a compliance filing, an accepted tariff sheet, and an effective service date can move the answer by years.
What to watch next
This analysis is current through 5 August 2026. The next checkpoints are unusually close:
- 17 August 2026 — responses are due in the six large-load show-cause proceedings.
- 18 August and 16 September 2026 — PJM has scheduled co-located-load stakeholder sessions.
- Later in 2026 — PJM's implementation materials point to additional filings, but those targets are plans, not approved effective dates.
- The effective-date decision — watch whether Interim NITS or NFCD can begin before the 2029 date PJM proposed and FERC sent back for support.
The enduring question is not “behind or in front?” It is: what may this site withdraw, what may its generator inject, how firm is the bargain, what happens when the on-site supply cannot carry the load, and which record proves each answer?
Evidence register
Sources and boundaries
The register below distinguishes the controlling record, exact-subject company reporting, bounded InfraSure context, visual provenance, and methodology. Each source is listed with what it supports—and what it does not.
- 01FERC, 195 FERC ¶ 61,209. Issued 18 June 2026. Used for the new transmission-service architecture, NFCD availability, cost treatment, operational consequences, 50 MW netting direction, further compliance, and the unresolved effective date.
- 02FERC, 193 FERC ¶ 61,217. Issued 18 December 2025. Used for the initial PJM replacement-rate findings and directives; later orders control where the framework changed.
- 03FERC, 189 FERC ¶ 61,078. Issued 1 November 2024. Used for the proposed 300-to-480 MW amendment, its rejection, and the failure to justify non-conforming provisions with controlling tariff evidence.
- 04FERC, 195 FERC ¶ 61,030. Issued 16 April 2026. Used for accepted and effective interconnection-side provisions, including below-nameplate requests, provisional service, surplus service, and existing acceleration provisions.
- 05Talen Energy, Form 10-Q for Q1 2026. Filed 5 May 2026. The AWS PPA definition reports that transition to the revised front-of-meter PPA occurred in April 2026.
- 06Talen Energy, Form 8-K and exhibits. Filed 11 June 2025. Used for the interim 300 MW description, planned transmission reconfiguration, three-party front-of-meter structure, and the 1,920 MW PPA contract boundary through 2042. Companion source.
- 07PJM, Co-Located Load Order Workshop presentation. Presented 30 July 2026. Used for PJM's current implementation posture, planned filings, workshop dates, and its summary of the June orders. Governing documents and FERC orders control. Companion source.
- 08FERC, six-market large-load show-cause fact sheet and PJM order. Issued 18 June 2026. Used for six tailored proceedings, shared reform questions, the 17 August 2026 response date, and the separation of PJM co-location into EL25-49. Companion source.
- 09Ted Shaffrey, Associated Press, 14 January 2025; carried by MPR News. Used only as a documentary view of the adjacent campus construction and nuclear plant.
- 10InfraSure plant 6103. Used to resolve the Susquehanna plant identity, PJM region, fuel class, and coordinates before retrieving the controlling external record.
- 11InfraSure data-center place dc_77d32ae9. Used only to route a provisional nearby place and expose the difference between a place object and a verified service relationship.
- 12InfraSure methodology package policy/rule_applicability_effective_timing. Used for the authority, disposition, effective-date, candidate-trigger, and blocked-claim gates.