Zunkerville BESS is a 207 MW Solar+Battery project in Texas, currently active.
Zunkerville Energy, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-12-01.
- Queue ID
- ERCOT-28INR0442
- Location
- Karnes, Texas
- Technology
- Solar+Battery
- Developer
- Zunkerville Energy, LLC
- Market / region
- ERCOT
- Point of interconnection
- 345kV BUS #5725 PAWNEE SWITCHING STATION
What stands out
1
Zunkerville BESS is a 207 MW Solar+Battery project in Texas with status active.
2
Zunkerville Energy, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-12-01.
Market and operating context
- Queue date
- 2025-09-22
- Proposed COD
- 2029-12-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.