Briefing on Zorro BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
154 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2026-08-31
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Zorro BESS is a 154 MW Battery project in Texas, currently active.

ZORRO BESS LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-08-31.

Queue ID
ERCOT-25INR0384
Location
Van Zandt, Texas
Technology
Battery
Developer
ZORRO BESS LLC
Market / region
ERCOT
Point of interconnection
138 kV Ben Wheeler (Bus# 6852)

What stands out

1

Zorro BESS is a 154 MW Battery project in Texas with status active.

2

ZORRO BESS LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-08-31.

Market and operating context

Queue date
2023-03-27
Proposed COD
2026-08-31
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Zorro BESS — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0384
LocationVan Zandt, Texas
TechnologyBattery
DeveloperZORRO BESS LLC
Market / regionERCOT
Point of interconnection138 kV Ben Wheeler (Bus# 6852)
Queue date2023-03-27
Proposed COD2026-08-31