Briefing on Zephyr Wind Project - 2.0

Entity Briefing
Generated Oct 17, 2026·Dataset freshness not reported
5 MW
Capacity
Operating
Current status
2020
Operating since
3
Generators
9.8%
Capacity factor
4 GWh
Annual generation
Briefing/plantOperating

Zephyr Wind Project - 2.0 is a 5 MW Onshore Wind Turbine asset in PJM Interconnection, currently Operating.

Zephyr Wind Project - 2.0 is reported in Ohio since 2020 under OEE XXX LLC. Available operating and financial measures include 9.8% capacity factor and 4 GWh annual generation; $1598/kW reported CapEx.

Location
Hancock, Ohio
Technology
Onshore Wind Turbine
Owner / parent
OEE XXX LLC
Operator
OEE XXX LLC
Grid
PJM Interconnection
Plant ID
62653

What stands out

1

Zephyr Wind Project - 2.0 is a 5 MW Onshore Wind Turbine asset in Ohio with status Operating.

2

Latest annual operating measures report 9.8% capacity factor and 4 GWh annual generation.

3

Available financial measures include $1598/kW CapEx.

Market and operating context

ISO / market
PJM Interconnection
Balancing authority
PJM Interconnection, LLC
NERC region
RFC
State rank
#10 of 24
National rank
#1253 of 1,442

Why it matters

For this asset in PJM Interconnection, operating status, generation, ownership, and linked events are the primary facts for performance and asset-level diligence. The exact chart and source-linked records below let the reader test those facts before moving to a deeper report.