Briefing on Yellow Cat Wind

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
262 MW
Proposed capacity
active
Current status
Wind
Technology
ERCOT
Market / region
2027-04-01
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Yellow Cat Wind is a 262 MW Wind project in Texas, currently active.

Yellow Cat Wind LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-04-01.

Queue ID
ERCOT-25INR0018
Location
Navarro, Texas
Technology
Wind
Developer
Yellow Cat Wind LLC
Market / region
ERCOT
Point of interconnection
Tap 345kV 1906 Venus - 68091 Navarro

What stands out

1

Yellow Cat Wind is a 262 MW Wind project in Texas with status active.

2

Yellow Cat Wind LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2027-04-01.

4

Latest linked story: “RWE and Rivian sign 15-year power purchase agreement for clean electricity supply from 127-megawatt Champion Wind Farm in Texas” (RWE, 2024-10-31).

Market and operating context

Queue date
2021-08-17
Proposed COD
2027-04-01
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Yellow Cat Wind — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0018
LocationNavarro, Texas
TechnologyWind
DeveloperYellow Cat Wind LLC
Market / regionERCOT
Point of interconnectionTap 345kV 1906 Venus - 68091 Navarro
Queue date2021-08-17
Proposed COD2027-04-01