Query
Wolf Summit Energy
Type
Entity Briefing
Entity
Wolf Summit Energy
Generated
2026-10-17T21:02:13.142Z

Briefing on Wolf Summit Energy

Entity Briefing
Generated Oct 17, 2026·Dataset freshness not reported
579 MW
Capacity
Planned
Current status
2
Generators
Briefing/plantPlanned

Wolf Summit Energy is a 579 MW Natural Gas Fired Combined Cycle asset in PJM Interconnection, currently Planned.

Wolf Summit Energy is reported in West Virginia under General Electric. Available operating and financial measures include $782/kW reported CapEx.

Location
Harrison, West Virginia
Technology
Natural Gas Fired Combined Cycle
Owner / parent
General Electric
Operator
Wolf Summit Energy LLC
Grid
PJM Interconnection
Plant ID
60206

What stands out

1

Wolf Summit Energy is a 579 MW Natural Gas Fired Combined Cycle asset in West Virginia with status Planned.

2

Available financial measures include $782/kW CapEx.

3

Latest linked story: “Kindle Energy and Blackstone Start Construction on 600MW CCGT Plant in Harrison County - News and Statistics” (IndexBox, 2026-04-28).

Market and operating context

ISO / market
PJM Interconnection
Balancing authority
PJM Interconnection, LLC
NERC region
RFC
State rank
#1 of 5
National rank
#432 of 2,025

Why it matters

For this asset in PJM Interconnection, operating status, generation, ownership, and linked events are the primary facts for performance and asset-level diligence. The exact chart and source-linked records below let the reader test those facts before moving to a deeper report.

Wolf Summit Energy — verified asset snapshot

FieldValue
LocationHarrison, West Virginia
TechnologyNatural Gas Fired Combined Cycle
Owner / parentGeneral Electric
OperatorWolf Summit Energy LLC
GridPJM Interconnection
Plant ID60206
ISO / marketPJM Interconnection
Balancing authorityPJM Interconnection, LLC