Wizard BESS is a 151 MW Battery project in Texas, currently active.
Wizard Energy Storage, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-02-14.
- Queue ID
- ERCOT-25INR0300
- Location
- Galveston, Texas
- Technology
- Battery
- Developer
- Wizard Energy Storage, LLC
- Market / region
- ERCOT
- Point of interconnection
- To the 138 kV League City Substation (#38920)
What stands out
1
Wizard BESS is a 151 MW Battery project in Texas with status active.
2
Wizard Energy Storage, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2026-02-14.
Market and operating context
- Queue date
- 2023-03-27
- Proposed COD
- 2026-02-14
- IA status
- IA Executed
- Study phase
- IA Executed