Briefing on WILLOW ROCK ENERGY STORAGE

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
620 MW
Proposed capacity
active
Current status
Battery
Technology
CAISO
Market / region
2030-07-01
Proposed COD
C13
Queue phase
Briefing/projectactive

WILLOW ROCK ENERGY STORAGE is a 620 MW Battery project in California, currently active.

The reported queue phase is C13. Proposed COD is 2030-07-01.

Queue ID
CAISO-1782
Location
Kern, California
Technology
Battery
Market / region
CAISO
Point of interconnection
Whirlwind Substation 230kV

What stands out

1

WILLOW ROCK ENERGY STORAGE is a 620 MW Battery project in California with status active.

2

The reported queue phase is C13; proposed COD is 2030-07-01.

3

Latest linked story: “US ROUNDUP: Hydrostor A-CAES project, Hawaiian Electric on Maui, Peregrine picks Wärtsilä for 500MWh Texas BESS” (Energy-Storage.News, 2025-12-24).

Market and operating context

Queue date
2020-04-15
Proposed COD
2030-07-01
IA status
IA Executed
Study phase
C13
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

WILLOW ROCK ENERGY STORAGE — verified asset snapshot

FieldValue
Queue IDCAISO-1782
LocationKern, California
TechnologyBattery
Market / regionCAISO
Point of interconnectionWhirlwind Substation 230kV
Queue date2020-04-15
Proposed COD2030-07-01
IA statusIA Executed