WILDHORSE ENERGY CENTER is a 122 MW Battery project in California, currently active.
The reported queue phase is C14. Proposed COD is 2030-05-04.
- Queue ID
- CAISO-1846
- Location
- Sonoma, California
- Technology
- Battery
- Market / region
- CAISO
- Point of interconnection
- Fulton 230 kV
What stands out
1
WILDHORSE ENERGY CENTER is a 122 MW Battery project in California with status active.
2
The reported queue phase is C14; proposed COD is 2030-05-04.
3
Latest linked story: “Large-scale solar farm in central WA gets green light from governor” (Washington State Standard, 2025-12-04).
Market and operating context
- Queue date
- 2021-04-15
- Proposed COD
- 2030-05-04
- IA status
- System Impact Study
- Study phase
- C14
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.