Briefing on WILDHORSE ENERGY CENTER

Entity Briefing
Generated Oct 13, 2026·Dataset freshness not reported
122 MW
Proposed capacity
active
Current status
Battery
Technology
CAISO
Market / region
2030-05-04
Proposed COD
C14
Queue phase
Briefing/projectactive

WILDHORSE ENERGY CENTER is a 122 MW Battery project in California, currently active.

The reported queue phase is C14. Proposed COD is 2030-05-04.

Queue ID
CAISO-1846
Location
Sonoma, California
Technology
Battery
Market / region
CAISO
Point of interconnection
Fulton 230 kV

What stands out

1

WILDHORSE ENERGY CENTER is a 122 MW Battery project in California with status active.

2

The reported queue phase is C14; proposed COD is 2030-05-04.

3

Latest linked story: “Large-scale solar farm in central WA gets green light from governor” (Washington State Standard, 2025-12-04).

Market and operating context

Queue date
2021-04-15
Proposed COD
2030-05-04
IA status
System Impact Study
Study phase
C14
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

WILDHORSE ENERGY CENTER — verified asset snapshot

FieldValue
Queue IDCAISO-1846
LocationSonoma, California
TechnologyBattery
Market / regionCAISO
Point of interconnectionFulton 230 kV
Queue date2021-04-15
Proposed COD2030-05-04
IA statusSystem Impact Study