What's the status of the 1 queue project linked to Leitrim Solar Park?
Type
Entity Briefing
Entity
Leitrim 1 Solar
State
AR
Generated
2026-10-11T02:27:34.538Z

Briefing on Leitrim 1 Solar

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
98 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2027-04-26
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Leitrim 1 Solar is a 98 MW Solar project in Texas, currently active.

Leitsol LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-04-26.

Queue ID
ERCOT-23INR0187
Location
Hill, Texas
Technology
Solar
Developer
Leitsol LLC
Market / region
ERCOT
Point of interconnection
tap 138kV 3522 Hillsboro - 3546 Whitney

What stands out

1

Leitrim 1 Solar is a 98 MW Solar project in Texas with status active.

2

Leitsol LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-04-26.

Market and operating context

Queue date
2021-01-26
Proposed COD
2027-04-26
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Leitrim 1 Solar — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0187
LocationHill, Texas
TechnologySolar
DeveloperLeitsol LLC
Market / regionERCOT
Point of interconnectiontap 138kV 3522 Hillsboro - 3546 Whitney
Queue date2021-01-26
Proposed COD2027-04-26