Briefing/projectactive
Armadillo Solar is a 200 MW Solar project in Texas, currently active.
Armadillo Solar Center, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-10-27.
- Queue ID
- ERCOT-21INR0421
- Location
- Navarro, Texas
- Technology
- Solar
- Developer
- Armadillo Solar Center, LLC
- Market / region
- ERCOT
- Point of interconnection
- 3387 Revolution 138kV
What stands out
1
Armadillo Solar is a 200 MW Solar project in Texas with status active.
2
Armadillo Solar Center, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2026-10-27.
4
Latest linked story: “Ørsted signs power purchase agreement with MSD” (Orsted, 2021-04-26).
Market and operating context
- Queue date
- 2019-08-28
- Proposed COD
- 2026-10-27
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.