Vineyard Mid-Atlantic West is a 1.3 GW Offshore Wind project in New York, currently active.
Vineyard Mid-Atlantic LLC is the reported developer. The reported queue phase is C24. Proposed COD is 2032-03-01.
- Queue ID
- NYISO-C24-003
- Location
- Nassau, New York
- Technology
- Offshore Wind
- Developer
- Vineyard Mid-Atlantic LLC
- Market / region
- NYISO
- Point of interconnection
- East Garden City 345kV
What stands out
Vineyard Mid-Atlantic West is a 1.3 GW Offshore Wind project in New York with status active.
Vineyard Mid-Atlantic LLC is the reported developer.
The reported queue phase is C24; proposed COD is 2032-03-01.
Latest linked story: “Trump said no new offshore wind farms. One just got underway — quietly” (Canary Media, 2025-04-09).
Market and operating context
- Queue date
- 2024-08-01
- Proposed COD
- 2032-03-01
- Study phase
- C24
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.