Briefing/projectactive
watermelon 8 energy storage is a 102 MW Battery project in Texas, currently active.
Tempus power management LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-03-01.
- Queue ID
- ERCOT-28INR0258
- Location
- Dallas, Texas
- Technology
- Battery
- Developer
- Tempus power management LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt 1.
What stands out
1
watermelon 8 energy storage is a 102 MW Battery project in Texas with status active.
2
Tempus power management LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-03-01.
Market and operating context
- Queue date
- 2025-02-14
- Proposed COD
- 2029-03-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.