Query
Waste Management Northern Oaks LFGTE
Type
Entity Briefing
Entity
Savannah Oaks Solar
Technology
gas
Generated
2026-10-10T16:19:31.053Z

Briefing on Savannah Oaks Solar

Entity Briefing
Generated Oct 10, 2026·Dataset freshness not reported
201 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2028-09-30
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Savannah Oaks Solar is a 201 MW Solar project in Texas, currently active.

Savannah Oaks Solar Project LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-09-30.

Queue ID
ERCOT-25INR0286
Location
Madison, Texas
Technology
Solar
Developer
Savannah Oaks Solar Project LLC
Market / region
ERCOT
Point of interconnection
Tap 345kV 46020 Limestone Plant - 967 Gibbons Creek

What stands out

1

Savannah Oaks Solar is a 201 MW Solar project in Texas with status active.

2

Savannah Oaks Solar Project LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-09-30.

Market and operating context

Queue date
2023-01-03
Proposed COD
2028-09-30
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Savannah Oaks Solar — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0286
LocationMadison, Texas
TechnologySolar
DeveloperSavannah Oaks Solar Project LLC
Market / regionERCOT
Point of interconnectionTap 345kV 46020 Limestone Plant - 967 Gibbons Creek
Queue date2023-01-03
Proposed COD2028-09-30