Briefing on Wagon Timber Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
172 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2028-10-16
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Wagon Timber Solar is a 172 MW Solar+Battery project in Texas, currently active.

Wagon Timber Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-10-16.

Queue ID
ERCOT-28INR0206
Location
Knox, Texas
Technology
Solar+Battery
Developer
Wagon Timber Solar, LLC
Market / region
ERCOT
Point of interconnection
6110 Munday East 138kV

What stands out

1

Wagon Timber Solar is a 172 MW Solar+Battery project in Texas with status active.

2

Wagon Timber Solar, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-10-16.

Market and operating context

Queue date
2024-12-19
Proposed COD
2028-10-16
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Wagon Timber Solar — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0206
LocationKnox, Texas
TechnologySolar+Battery
DeveloperWagon Timber Solar, LLC
Market / regionERCOT
Point of interconnection6110 Munday East 138kV
Queue date2024-12-19
Proposed COD2028-10-16