Briefing on Vinton Energy Storage

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
42 MW
Proposed capacity
suspended
Current status
Battery
Technology
PJM
Market / region
2026-12-31
Proposed COD
IA Executed
Queue phase
Briefing/projectsuspended

Vinton Energy Storage is a 42 MW Battery project in Ohio, currently suspended.

The reported queue phase is IA Executed. Proposed COD is 2026-12-31.

Queue ID
PJM-AE1-093
Location
Vinton, Ohio
Technology
Battery
Market / region
PJM
Point of interconnection
Elk 138 kV

What stands out

1

Vinton Energy Storage is a 42 MW Battery project in Ohio with status suspended.

2

The reported queue phase is IA Executed; proposed COD is 2026-12-31.

Market and operating context

Queue date
2018-08-31
Proposed COD
2026-12-31
IA status
IA Executed
Study phase
IA Executed
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Vinton Energy Storage — verified asset snapshot

FieldValue
Queue IDPJM-AE1-093
LocationVinton, Ohio
TechnologyBattery
Market / regionPJM
Point of interconnectionElk 138 kV
Queue date2018-08-31
Proposed COD2026-12-31
IA statusIA Executed