Briefing/projectactive
Vermilion Grove Wind is a 255 MW Wind project in Indiana, currently active.
Vermilion Grove Wind, LLC is the reported developer. The reported queue phase is TC1. Proposed COD is 2022-12-31.
- Queue ID
- PJM-AF1-204
- Location
- Vermillion, Indiana
- Technology
- Wind
- Developer
- Vermilion Grove Wind, LLC
- Market / region
- PJM
- Point of interconnection
- Eugene 345 kV
What stands out
1
Vermilion Grove Wind is a 255 MW Wind project in Indiana with status active.
2
Vermilion Grove Wind, LLC is the reported developer.
3
The reported queue phase is TC1; proposed COD is 2022-12-31.
Market and operating context
- Queue date
- 2019-09-25
- Proposed COD
- 2022-12-31
- IA status
- System Impact Study
- Study phase
- TC1
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.