Velociraptor Solar II is a 252 MW Solar+Battery project in Texas, currently active.
Greyhound Solar 3 LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-12-01.
- Queue ID
- ERCOT-28INR0322
- Location
- Ector, Texas
- Technology
- Solar+Battery
- Developer
- Greyhound Solar 3 LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap south bus Odessa EHV SW (11028) - Wolf Switch (11010) 345KV section at (31.740371, -102.502076)
What stands out
1
Velociraptor Solar II is a 252 MW Solar+Battery project in Texas with status active.
2
Greyhound Solar 3 LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-12-01.
Market and operating context
- Queue date
- 2025-05-27
- Proposed COD
- 2029-12-01
- IA status
- Facility Study
- Study phase
- Facility Study