Briefing on Upper Beaver Falls Project

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
2 MW
Capacity
Operating
Current status
1985
Operating since
1
Generators
45.8%
Capacity factor
6 GWh
Annual generation
Briefing/plantOperating

Upper Beaver Falls Project is a 2 MW Conventional Hydroelectric asset in NYISO (New York), currently Operating.

Upper Beaver Falls Project is reported in New York since 1985 under Eagle Creek Renewable Energy, LLC. Available operating and financial measures include 45.8% capacity factor and 6 GWh annual generation; $2294/kW reported CapEx.

Location
Lewis, New York
Technology
Conventional Hydroelectric
Owner / parent
Eagle Creek Renewable Energy, LLC
Operator
Eagle Creek Renewable Energy, LLC
Grid
NYISO (New York)
Plant ID
10490

What stands out

1

Upper Beaver Falls Project is a 2 MW Conventional Hydroelectric asset in New York with status Operating.

2

Latest annual operating measures report 45.8% capacity factor and 6 GWh annual generation.

3

Available financial measures include $2294/kW CapEx.

Market and operating context

ISO / market
NYISO (New York)
Balancing authority
New York Independent System Operator
NERC region
NPCC
State rank
#149 of 165
National rank
#1304 of 1,462

Why it matters

For this asset in NYISO (New York), operating status, generation, ownership, and linked events are the primary facts for performance and asset-level diligence. The exact chart and source-linked records below let the reader test those facts before moving to a deeper report.