Briefing on Union City Storage II

Entity Briefing
Generated Oct 10, 2026·Dataset freshness not reported
100 MW
Proposed capacity
active
Current status
Battery
Technology
Southeast
Market / region
2022-11-30
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Union City Storage II is a 100 MW Battery project in Georgia, currently active.

The reported queue phase is Facility Study. Proposed COD is 2022-11-30.

Queue ID
GTC-GI-133
Location
Fulton, Georgia
Technology
Battery
Market / region
Southeast
Point of interconnection
Union City substation

What stands out

1

Union City Storage II is a 100 MW Battery project in Georgia with status active.

2

The reported queue phase is Facility Study; proposed COD is 2022-11-30.

3

Latest linked story: “Georgia Power gets PSC’s go-ahead on $16B data center power plant expansion” (AJC.com, 2025-12-19).

Market and operating context

Queue date
2019-12-11
Proposed COD
2022-11-30
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Union City Storage II — verified asset snapshot

FieldValue
Queue IDGTC-GI-133
LocationFulton, Georgia
TechnologyBattery
Market / regionSoutheast
Point of interconnectionUnion City substation
Queue date2019-12-11
Proposed COD2022-11-30
IA statusFacility Study