Briefing on TULE WIND

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
259 MW
Proposed capacity
active
Current status
Wind+Battery
Technology
CAISO
Market / region
2030-10-31
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

TULE WIND is a 259 MW Wind+Battery project in California, currently active.

The reported queue phase is IA Executed. Proposed COD is 2030-10-31.

Queue ID
CAISO-32
Location
San Diego, California
Technology
Wind+Battery
Market / region
CAISO
Point of interconnection
Boulevard East Substation 138 kV

What stands out

1

TULE WIND is a 259 MW Wind+Battery project in California with status active.

2

The reported queue phase is IA Executed; proposed COD is 2030-10-31.

3

Latest linked story: “Inside a wind farm producing renewable energy for San Diego County” (cbs8.com, 2022-06-20).

Market and operating context

Queue date
2004-05-24
Proposed COD
2030-10-31
IA status
IA Executed
Study phase
IA Executed
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

TULE WIND — verified asset snapshot

FieldValue
Queue IDCAISO-32
LocationSan Diego, California
TechnologyWind+Battery
Market / regionCAISO
Point of interconnectionBoulevard East Substation 138 kV
Queue date2004-05-24
Proposed COD2030-10-31
IA statusIA Executed