Triple B Solar Alt#2 is a 150 MW Solar project in Texas, currently active.
Triple B Solar LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-07-01.
- Queue ID
- ERCOT-24INR0069
- Location
- Lampasas, Texas
- Technology
- Solar
- Developer
- Triple B Solar LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138kV 7066 Adamsville - 7064 Lampasas
What stands out
1
Triple B Solar Alt#2 is a 150 MW Solar project in Texas with status active.
2
Triple B Solar LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-07-01.
4
Latest linked story: “Texas will host the largest solar project in the US” (Electrek, 2020-11-20).
Market and operating context
- Queue date
- 2021-06-10
- Proposed COD
- 2028-07-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.