Trinidad ESS Addition in Texas queue pipeline — 1 projects by technology and status
Type
Entity Briefing
Entity
FGE Texas 2 Gas
State
TX
Technology
battery
Generated
2026-10-12T00:52:22.346Z

Briefing on FGE Texas 2 Gas

Entity Briefing
Generated Oct 12, 2026·Dataset freshness not reported
743 MW
Proposed capacity
suspended
Current status
Gas
Technology
ERCOT
Market / region
2028-05-30
Proposed COD
IA Pending
Queue phase
Briefing/projectsuspended

FGE Texas 2 Gas is a 743 MW Gas project in Texas, currently suspended.

FGE Power is the reported developer. The reported queue phase is IA Pending. Proposed COD is 2028-05-30.

Queue ID
ERCOT-17INR0010
Location
Mitchell, Texas
Technology
Gas
Developer
FGE Power
Market / region
ERCOT
Point of interconnection
Tap 345kV 1030 Morgan – 1058 Longshore

What stands out

1

FGE Texas 2 Gas is a 743 MW Gas project in Texas with status suspended.

2

FGE Power is the reported developer.

3

The reported queue phase is IA Pending; proposed COD is 2028-05-30.

Market and operating context

Queue date
2014-02-10
Proposed COD
2028-05-30
IA status
IA Pending
Study phase
IA Pending

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

FGE Texas 2 Gas — verified asset snapshot

FieldValue
Queue IDERCOT-17INR0010
LocationMitchell, Texas
TechnologyGas
DeveloperFGE Power
Market / regionERCOT
Point of interconnectionTap 345kV 1030 Morgan – 1058 Longshore
Queue date2014-02-10
Proposed COD2028-05-30