Briefing on TRACY - ADDITIONAL CAPACITY

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
20 MW
Proposed capacity
active
Current status
Gas
Technology
CAISO
Market / region
2012-05-31
Proposed COD
C02
Queue phase
Briefing/projectactive

TRACY - ADDITIONAL CAPACITY is a 20 MW Gas project in California, currently active.

The reported queue phase is C02. Proposed COD is 2012-05-31.

Queue ID
CAISO-606
Location
San Joaquin, California
Technology
Gas
Market / region
CAISO
Point of interconnection
Schulte Switching Station 115kV bus

What stands out

1

TRACY - ADDITIONAL CAPACITY is a 20 MW Gas project in California with status active.

2

The reported queue phase is C02; proposed COD is 2012-05-31.

Market and operating context

Queue date
2010-02-01
Proposed COD
2012-05-31
IA status
IA Executed
Study phase
C02
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

TRACY - ADDITIONAL CAPACITY — verified asset snapshot

FieldValue
Queue IDCAISO-606
LocationSan Joaquin, California
TechnologyGas
Market / regionCAISO
Point of interconnectionSchulte Switching Station 115kV bus
Queue date2010-02-01
Proposed COD2012-05-31
IA statusIA Executed