Briefing/projectactive
TOCE GA 1 Solar is a 125 MW Solar project in Georgia, currently active.
The reported queue phase is System Impact Study. Proposed COD is 2026-09-01.
- Queue ID
- GTC-GI-177
- Location
- Burke, Georgia
- Technology
- Solar
- Market / region
- Southeast
- Point of interconnection
- Greens Cut - Greens Cut Junction 115 kV Tap
What stands out
1
TOCE GA 1 Solar is a 125 MW Solar project in Georgia with status active.
2
The reported queue phase is System Impact Study; proposed COD is 2026-09-01.
3
Latest linked story: “A new Georgia data center could be powered by RICE. It’s not the kind you eat.” (AJC.com, 2025-12-19).
Market and operating context
- Queue date
- 2023-08-03
- Proposed COD
- 2026-09-01
- IA status
- System Impact Study
- Study phase
- System Impact Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.