Briefing/projectactive
Tierra Loma Storage is a 200 MW Battery project in Texas, currently active.
Tierra Loma Solar, LLC is the reported developer. Proposed COD is 2029-09-01.
- Queue ID
- ERCOT-29INR0280
- Location
- Crane, Texas
- Technology
- Battery
- Developer
- Tierra Loma Solar, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345 kV #18668 ROCK DRAW - #76000 NORTH MCCAMEY ckt 1
What stands out
1
Tierra Loma Storage is a 200 MW Battery project in Texas with status active.
2
Tierra Loma Solar, LLC is the reported developer.
3
proposed COD is 2029-09-01.
4
Latest linked story: “SDG&E to build microgrid and storage project in Tierrasanta” (San Diego Union-Tribune, 2022-10-12).
Market and operating context
- Queue date
- 2026-02-19
- Proposed COD
- 2029-09-01
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.