Briefing on Three Ranches BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
103 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2029-12-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Three Ranches BESS is a 103 MW Solar+Battery project in Texas, currently active.

Three Ranches Energy LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-12-01.

Queue ID
ERCOT-29INR0170
Location
Brewster, Texas
Technology
Solar+Battery
Developer
Three Ranches Energy LLC
Market / region
ERCOT
Point of interconnection
TAP 138kV #6680 Alamitto Creek - #60444 Hayter Ranch

What stands out

1

Three Ranches BESS is a 103 MW Solar+Battery project in Texas with status active.

2

Three Ranches Energy LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2029-12-01.

Market and operating context

Queue date
2025-08-21
Proposed COD
2029-12-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Three Ranches BESS — verified asset snapshot

FieldValue
Queue IDERCOT-29INR0170
LocationBrewster, Texas
TechnologySolar+Battery
DeveloperThree Ranches Energy LLC
Market / regionERCOT
Point of interconnectionTAP 138kV #6680 Alamitto Creek - #60444 Hayter Ranch
Queue date2025-08-21
Proposed COD2029-12-01