Briefing/projectactive
TEXAS SOLAR NOVA 3 is a 200 MW Solar project in Texas, currently active.
Clearway Energy is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2026-01-31.
- Queue ID
- ERCOT-22INR0215
- Location
- Kent, Texas
- Technology
- Solar
- Developer
- Clearway Energy
- Market / region
- ERCOT
- Point of interconnection
- tap 345kV 11305 Dermott - 59904 Cottonwood
What stands out
1
TEXAS SOLAR NOVA 3 is a 200 MW Solar project in Texas with status active.
2
Clearway Energy is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2026-01-31.
Market and operating context
- Queue date
- 2019-06-24
- Proposed COD
- 2026-01-31
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.