Briefing on WATER ROCK SOLAR 2

Entity Briefing
Generated Oct 9, 2026·Dataset freshness not reported
1 GW
Proposed capacity
active
Current status
Solar+Battery
Technology
CAISO
Market / region
2028-12-01
Proposed COD
C14
Queue phase
Briefing/projectactive

WATER ROCK SOLAR 2 is a 1 GW Solar+Battery project in Nevada, currently active.

The reported queue phase is C14. Proposed COD is 2028-12-01.

Queue ID
CAISO-2146
Location
Nye, Nevada
Technology
Solar+Battery
Market / region
CAISO
Point of interconnection
Gamebird Substation 230 kV

What stands out

1

WATER ROCK SOLAR 2 is a 1 GW Solar+Battery project in Nevada with status active.

2

The reported queue phase is C14; proposed COD is 2028-12-01.

3

Latest linked story: “Feds auction NV public land leases for record $105 million, highlighting solar boom” (Nevada Current, 2023-07-05).

Market and operating context

Queue date
2021-04-15
Proposed COD
2028-12-01
IA status
System Impact Study
Study phase
C14
Service type
ERIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

WATER ROCK SOLAR 2 — verified asset snapshot

FieldValue
Queue IDCAISO-2146
LocationNye, Nevada
TechnologySolar+Battery
Market / regionCAISO
Point of interconnectionGamebird Substation 230 kV
Queue date2021-04-15
Proposed COD2028-12-01
IA statusSystem Impact Study